Milestones

May 2009 – Auckland Regional Council agrees to make the new site available.

June 2009 – Jasmax invited to prepare designs for consulting with the local community.

October 2009 – Muriwai Lifeguard Service Amenities Trust established and assumes responsibility for the project.

June 2010 – RDC issues the Trust with its resource consent.  The ARC confirms $450,000 funding for siteworks and utility reticulation.  RDC confirms $150,000 to allow the Trust to commission final architectural and technical consultancy to obtain a building permit.

October 2010- RDC issues the Trust with a building permit.

November 2010 – The Trust secures a head contractor.